Dividing AV Tender Responsibilities: Who Prepares Power, Network and Mounting Locations?
Clearly defining AV tender work, responsible parties, readiness deadlines and verification methods.
When procuring an audiovisual system, the technical specification should state who prepares the infrastructure needed for operation. If neither party is assigned the projector mounting point, network port or power outlet, delivering equipment cannot ensure a complete installation. An unclear scope may also cause suppliers to include different works in their prices.
What Should the Responsibility Matrix Say?
For each entry, specify four things: what must be done, who does it, when it must be ready and how readiness is demonstrated. Give the point or device the same number it has on the drawing. For example, “the purchaser prepares the network” does not fully define the scope. A clearer statement is: “The purchaser’s IT team activates network port N-07 shown on the drawing before installation starts; the AV supplier connects the device and checks connectivity together with IT.”
Separate works involving different parties in particular: preparing the cable route and containment, installing and terminating cables, providing power points, configuring the network and preparing mounting structures. Parties may vary from project to project. The US public AV guide specification is a reference example for coordination; the tender documents themselves define the scope for a particular procurement.
Practical Example: Installing a Projector in an Auditorium
- Mounting point: The construction party prepares the agreed location in accordance with the structural design. The AV supplier provides equipment and mount data in advance and prepares its own installation drawing. - Power and signal route: The electrical works party prepares the appropriate power point. The specification separately states who prepares the cable route and who terminates and tests the signal cable. - Readiness check: Before installation, the parties compare the drawing with the site. If a point is elsewhere or a cable route is obstructed, they record the change before opening a finished ceiling becomes necessary.
How Do We Use the Matrix to Compare Offers?
In the offer form, separately identify the AV supplier’s works and infrastructure provided by the client or another contractor. Transfer the same entries to the pre-start checklist. One document then answers two practical questions: what the supplier is pricing and what should be ready on site. This work is based on a technical site survey before AV procurement.