An AV tender requirement for “8 PoE+ ports” alone is insufficient. Specify separately how many ports need a particular PoE standard and the total power the switch must deliver to those ports simultaneously. Calculate the budget using watts allocated at the switch, not just devices’ average consumption.
Why Does Port Count Not Equal Power Budget?
A port may support IEEE 802.3at (PoE+), while the switch power supply lacks sufficient capacity to fully load all such ports. Power delivered at a switch port also differs from the power reaching the device at the far end of the cable. The Cisco deployment guide gives these PoE+ figures as 30 W at the switch and 25.5 W at the device. A switch may allocate power by device class or negotiated demand; the technical offer should also make this mechanism clear.
Calculation Example: Six Active and Two Future Ports
If you plan to allocate 30 W per port for six AV devices, the current simultaneous budget is 6 × 30 W = 180 W. If you need two more ports for future devices of the same class, the full planned budget is 8 × 30 W = 240 W. An eight-port PoE+ switch with a total budget of 150 W is therefore insufficient for this particular scenario. 240 W is the result of this example, not a mandatory value for every project.
What Should the Technical Specification Say?
For this example, the requirement could read: “At least 8 IEEE 802.3at ports, each capable of allocating up to 30 W, with a combined PoE budget of at least 240 W in the proposed power supply configuration.” Manufacturer documentation for the exact model and power configuration is useful evidence of compliance. If full load must be maintained after a power supply failure, state this separately as a measurable condition.
How Do We Verify It at Delivery?
Record available, allocated and remaining PoE power from the switch management interface; the Cisco PoE troubleshooting document provides an example of this check. Run the active devices simultaneously, including after restarting. A test without the two future ports confirms only the operation of six devices; a practical test of the full 240 W capability also requires an appropriate test load.
The PoE budget checks the power requirement. Assess network bandwidth and video stream management separately when selecting an AV-over-IP switch.